According to the Rongcheng Municipal Government, on February 25th, the Kangde Carbon Valley Project, a key project of Shandong Rongcheng City, was fully started.
A total of 5 production lines will be built in the first phase of the project. The two 12k production lines will be completed before the end of February. The other three production lines, public and auxiliary facilities and office buildings will be completed in mid-March. The foundation is strong.
It is understood that the civil works of the first phase of the project will be completed by the end of July, equipment installation will be completed, and production will be completed by the end of December. The matching natural gas cogeneration project is also accelerating. During the year, two new gas-fired steam combined cycle units will be built to achieve efficient energy utilization.
------------------------------------------------------------------------------------------------------------------
XIAMEN LFT COMPOSITE PLASTIC CO.,LTD.
Focus on (LFT-G, LFRT) R&D and production: PA, PP, TPU, PPS, PBT, PPA long glass fiber & carbon fiber continuous infiltration thermoplastic composite reinforcement series engineering plastics
If you need more information, please feel free to contact me.
Mike Lee
Email: sale02@lfrtplastic.com
Mobile phone : +86-180-5026-9764 (wechat / whatsapp/ skype)
Add:No.27 Hongxi Road, Tiangong Chuangxin Technology Park, Maxiang Town, Xiang'an Dist., Xiamen, Fujian, China.